SRS Watch News Flash
Ruling Throws Spanner into NNSA’s Effort to Convert MOX to an Unneeded Nuclear Bomb Facility (to Make Plutonium “Pits” For Nuclear Weapons)
With Court Ruling, MOX Zombie Project Allowed to Stumble Onward to Eventual, Inevitable Termination, with more needless Waste of Taxpayer Money
Preliminary Injunction linked here
Columbia, SC – A judge with the federal district court in Columbia, South Carolina this evening issued a “preliminary injunction” to halt the termination of the mismanaged plutonium fuel (MOX) project at the Savannah River Site in South Carolina. The preliminary injunction had been requested by the State of South Carolina on May 25, 2018.
Post in court docket on June 7, 2018: “ORDER granting 5 the State’s Motion for Preliminary Injunction and ordering the State to pay $100.00 bond by Friday, June 8, 2018 at 4 p.m. Signed by Honorable J Michelle Childs on 06/07/2018.(vdou, ) (Main Document 23 replaced on 6/7/2018) (mbro, ). (Entered: 06/07/2018)”