• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
  • Skip to footer

Savannah River Site

Monitors a host of energy and nuclear issues from a public interest perspective

  • Home
  • About Us
  • News
  • SRS Watch News
  • Library
    • Department of Energy
    • General Documents
    • Freedom of Information Act Documents
  • Photos
  • Show Search
Hide Search

GAO: SRS Plutonium Bomb Plant Delays Mount and Costs Soar, Per Usual DOE Methodology, Feb. 26, 2026 report

SRSW · February 28, 2026 ·

DOE’s “Nuclear Security Enterprise” – Yes, it’s a busine$$ enterprise

“Assessments of NNSA Major Projects”

Government Accountability Office – GAO-26-107777, February 26, 2026

GAO observes that the SRS Plutonium Bomb Plant operation has slipped to 2035 and is likely to slip further and that costs are soaring, following the usual DOE/contractor formula for such budget-busting projects that threaten national security:

SRPPF Main Process Building (Savannah River Site). As part of its
second revised tailoring strategy for the overall SRPPF project, in
October 2024, NNSA transferred the scope of three other projects to
the MPB project. The revised tailoring strategy allows the project to
establish performance baselines with a design maturity of 60 percent
instead of 90 percent as would otherwise be required by DOE’s
project management order. The revised strategy also allows the
project to begin construction before establishing performance
baselines. Prior to the revised tailoring strategy, officials told us that
NNSA required the project to implement key design changes, such as
revising the scope to address single points of failure and add more
space for future capabilities, and that the scope has been stable since
that time. However, they stated that they continue to experience
design challenges, such as difficulties hiring qualified design
engineers and the inability of the contractor to meet performance
targets. Due in part to these issues, NNSA officials said the project’s
final design review could be delayed by 6 months (from March 2026 to
September 2026). In addition, as part of the revised tailoring strategy,
NNSA officials told us that they approved 10 early procurement and
site preparation work packages, which allowed the project to start
construction earlier on lower risk activities and spread the work out
over time. However, NNSA was not able to fully implement the revised
strategy related to these packages because of delays receiving
design packages from the contractor, according to officials. Similarly,
officials said the package the contractor submitted in May 2025 for an
independent cost estimate was insufficient to conduct the estimate. A
resubmittal is scheduled for early 2026, at which time the project’s
design should be matured closer to 90 percent, according to officials.

As of June 2025, NNSA was in the process of updating the project’s
cost and schedule estimates. According to NNSA’s fiscal year 2026
budget justification, the project’s cost may increase to over $22 billion
(up from a preliminary cost range of $6.9 billion to $11.1 billion) with a
completion date of September 2035 (the top of the preliminary
schedule range). However, officials told us the completion date may
be delayed. They said that they plan to submit revised cost and
schedule estimates for senior NNSA management review and
approval by September 2026.

(page 25)

—-

page 55:  “As of June 2025, NNSA officials were reviewing the
project’s cost and schedule estimates due to replanning
efforts. Specifically, the overall SRPPF project is
undergoing a revised alternative selection process due to
concerns with potential cost increases and delays.
According to NNSA’s fiscal year 2026 budget justification,
the MPB project is expected to cost over $22 billion and
be completed by September 2035. NNSA officials said
they plan to submit revised cost and schedule estimates
for approval by September 2026.”

Filed Under: Latest News

Primary Sidebar

Subscribe to Updates via Email

Enter your email address to subscribe to updates and receive notifications of new posts by email.

Recent Posts

  • SRS Watch Unleashes Comment Against DOE Effort to Avoid NEPA for “Advanced Nuclear Reactors,” March 4, 2026
  • GAO: SRS Plutonium Bomb Plant Delays Mount and Costs Soar, Per Usual DOE Methodology, Feb. 26, 2026 report
  • Paddle & Boogie to Stop the SRS Plutonium Bomb Plant, Augusta, GA Canal, March 28, 2026, with Music
  • Workers at SRS Plutonium Bomb Plant almost Sliced to Ribbons by Robot “Hydroblasting” External Wall: DOE & DNFSB Reports
  • Plutonium Shipment Secrecy – Ripe for Comments in the Plutonium-Pit-Production Draft Programmatic EIS in May 2026

Categories

  • Events
  • Latest News
  • SRS Watch News

Archives

  • March 2026
  • February 2026
  • November 2025
  • October 2025
  • September 2025
  • August 2025
  • July 2025
  • May 2025
  • April 2025
  • March 2025
  • February 2025
  • January 2025
  • December 2024
  • November 2024
  • October 2024
  • September 2024
  • May 2024
  • April 2024
  • March 2024
  • February 2024
  • January 2024
  • December 2023
  • November 2023
  • October 2023
  • September 2023
  • August 2023
  • July 2023
  • June 2023
  • May 2023
  • April 2023
  • March 2023
  • February 2023
  • January 2023
  • November 2022
  • October 2022
  • September 2022
  • July 2022
  • June 2022
  • May 2022
  • April 2022
  • March 2022
  • February 2022
  • January 2022
  • December 2021
  • November 2021
  • October 2021
  • September 2021
  • August 2021
  • July 2021
  • June 2021
  • May 2021
  • April 2021
  • March 2021
  • February 2021
  • January 2021
  • December 2020
  • November 2020
  • October 2020
  • September 2020
  • August 2020
  • July 2020
  • June 2020
  • May 2020
  • April 2020
  • March 2020
  • February 2020
  • January 2020
  • December 2019
  • November 2019
  • October 2019
  • September 2019
  • August 2019
  • July 2019
  • June 2019
  • May 2019
  • April 2019
  • March 2019
  • February 2019
  • January 2019
  • December 2018
  • November 2018
  • October 2018
  • September 2018
  • August 2018
  • July 2018
  • June 2018
  • May 2018
  • April 2018
  • March 2018
  • February 2018
  • January 2018
  • December 2017
  • November 2017
  • October 2017
  • September 2017
  • August 2017
  • July 2017
  • June 2017
  • May 2017
  • March 2017
  • February 2017
  • January 2017
  • December 2016
  • November 2016
  • October 2016
  • September 2016
  • August 2016
  • July 2016
  • June 2016
  • May 2016
  • April 2016
  • March 2016
  • February 2016
  • January 2016
  • December 2015
  • November 2015
  • October 2015
  • September 2015
  • August 2015
  • July 2015
  • June 2015
  • May 2015
  • April 2015
  • March 2015
  • February 2015
  • January 2015
  • December 2014
  • November 2014
  • October 2014
  • September 2014
  • August 2014
  • July 2014
  • June 2014
  • May 2014
  • April 2014
  • March 2014

SAVANNAH RIVER SITE WATCH
1112 Florence Street, COLUMBIA, SC 29201  | 803-834-3084  – srswatch@gmail.com

Footer

The information produced on this website is the sole property of SRS Watch unless otherwise noted and may be reproduced or quoted if credit is given to SRS Watch. Materials published on this website are for non-profit public interest purposes only. SRS Watch is a registered corporation in South Carolina and in December 2014 and has obtained non-profit 501(c)(3) public -interest organization status from the IRS. SRS Watch is responsible for all material published on this website. We strive to be accurate in all material produced. For inquiries, comments or corrections, please contact us at srswatch@gmail.com or 803-834-3084. Donations are most welcome and are tax deductible. Mailing address: Savannah River Site Watch, 1112 Florence Street, Columbia, SC 29201. This site or product includes IP2Location LITE data available from https://lite.ip2location.com.

©SRS Watch 2019  All Rights Reserved in All Media.