• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
  • Skip to footer

Savannah River Site

Monitors a host of energy and nuclear issues from a public interest perspective

  • Home
  • About Us
  • News
  • SRS Watch News
  • Library
    • Department of Energy
    • General Documents
    • Freedom of Information Act Documents
  • Photos
  • Show Search
Hide Search

H-Canyon Reprocessing Plant Poses Risks

SRSW · November 24, 2015 ·

Defense Nuclear Facilities Safety Board (DNFSB) Express Concerns about Return to H-Canyon Operations at SRS — October 23, 2015 weekly report (posted November 24, 2015) and linked here

Is Restart and Operation of the HB-Line – to Produce Unneeded Plutonium Oxide for the Failed MOX Program – SAFE?

“While many instances of procedural improvements and opportunities for improving conduct of operations have been identified, the site reps have mixed feelings about the overall effort. The all-encompassing scope included some low value actions (e.g., stopping office trash pickup or repair of copy machines, deliberate operations for general counsel). Managers across the site are spending many hours in management review team meetings reviewing hundreds of management field observations or MFOs (e.g., HB-Line stated they have a backlog of 200 MFOs) of mostly low hazard activities. These MFOs are creating a huge wave of procedure change requests (PCR). For example, H-Canyon reports that they need to revise at least 500 procedures. Considering how few procedure writers are at SRS and how inadequate procedure validation has been a common problem in past events, trying to push this many changes through the system may be setting up future procedure quality issues. Addressing the lessons learned from the HB-Line RCA is a key corrective action, but the reality is that even after interviewing the workers involved in the event, nobody really knows how/why the group made certain decisions so some of the RCA is likely to be speculative. Suspending processes for weeks or months without using the down time to train, practice, and drill the workers may result in a loss of proficiency and equipment issues often occur when they are restarted after sitting idle. For example, HB-Line had just qualified four rotating shift crews on plutonium operations, but they had little opportunity to conduct any actual processing before the pause took effect.”

[RCA = root cause analysis]

DNFSB weekly report of October 23, 2015 linked here

—–

HB-Line goes back into “deliberate operations” – November 23, 2015

​- see SRS update linked here

SRS has notified the public that HB-Line, which had an incident during production of plutonium oxide for the failed MOX project, has been brought back into operation.  Given two criticality related incidents this year in the facility, all eyes will be on operations.  HB-Line is slated to produced 3.7 metric tons of plutonium oxide but has so far produced only 9.6 kilograms, or only 0.3% of its production mission.

See SRS Watch’s November 12, 2015 report
​”H-Canyon Folly, Plutonium Failure,”on HB-Line problems and no need for it to operate to produce plutonium oxide “feed stock” for the MOX boondoggle, which has been kept on a shutdown track by Congress (as its funding level – $345 million/year – is barely enough to keep it alive).

Filed Under: SRS Watch News

Primary Sidebar

Subscribe to Updates via Email

Enter your email address to subscribe to updates and receive notifications of new posts by email.

Recent Posts

  • SRS Watch Unleashes Comment Against DOE Effort to Avoid NEPA for “Advanced Nuclear Reactors,” March 4, 2026
  • GAO: SRS Plutonium Bomb Plant Delays Mount and Costs Soar, Per Usual DOE Methodology, Feb. 26, 2026 report
  • Paddle & Boogie to Stop the SRS Plutonium Bomb Plant, Augusta, GA Canal, March 28, 2026, with Music
  • Workers at SRS Plutonium Bomb Plant almost Sliced to Ribbons by Robot “Hydroblasting” External Wall: DOE & DNFSB Reports
  • Plutonium Shipment Secrecy – Ripe for Comments in the Plutonium-Pit-Production Draft Programmatic EIS in May 2026

Categories

  • Events
  • Latest News
  • SRS Watch News

Archives

  • March 2026
  • February 2026
  • November 2025
  • October 2025
  • September 2025
  • August 2025
  • July 2025
  • May 2025
  • April 2025
  • March 2025
  • February 2025
  • January 2025
  • December 2024
  • November 2024
  • October 2024
  • September 2024
  • May 2024
  • April 2024
  • March 2024
  • February 2024
  • January 2024
  • December 2023
  • November 2023
  • October 2023
  • September 2023
  • August 2023
  • July 2023
  • June 2023
  • May 2023
  • April 2023
  • March 2023
  • February 2023
  • January 2023
  • November 2022
  • October 2022
  • September 2022
  • July 2022
  • June 2022
  • May 2022
  • April 2022
  • March 2022
  • February 2022
  • January 2022
  • December 2021
  • November 2021
  • October 2021
  • September 2021
  • August 2021
  • July 2021
  • June 2021
  • May 2021
  • April 2021
  • March 2021
  • February 2021
  • January 2021
  • December 2020
  • November 2020
  • October 2020
  • September 2020
  • August 2020
  • July 2020
  • June 2020
  • May 2020
  • April 2020
  • March 2020
  • February 2020
  • January 2020
  • December 2019
  • November 2019
  • October 2019
  • September 2019
  • August 2019
  • July 2019
  • June 2019
  • May 2019
  • April 2019
  • March 2019
  • February 2019
  • January 2019
  • December 2018
  • November 2018
  • October 2018
  • September 2018
  • August 2018
  • July 2018
  • June 2018
  • May 2018
  • April 2018
  • March 2018
  • February 2018
  • January 2018
  • December 2017
  • November 2017
  • October 2017
  • September 2017
  • August 2017
  • July 2017
  • June 2017
  • May 2017
  • March 2017
  • February 2017
  • January 2017
  • December 2016
  • November 2016
  • October 2016
  • September 2016
  • August 2016
  • July 2016
  • June 2016
  • May 2016
  • April 2016
  • March 2016
  • February 2016
  • January 2016
  • December 2015
  • November 2015
  • October 2015
  • September 2015
  • August 2015
  • July 2015
  • June 2015
  • May 2015
  • April 2015
  • March 2015
  • February 2015
  • January 2015
  • December 2014
  • November 2014
  • October 2014
  • September 2014
  • August 2014
  • July 2014
  • June 2014
  • May 2014
  • April 2014
  • March 2014

SAVANNAH RIVER SITE WATCH
1112 Florence Street, COLUMBIA, SC 29201  | 803-834-3084  – srswatch@gmail.com

Footer

The information produced on this website is the sole property of SRS Watch unless otherwise noted and may be reproduced or quoted if credit is given to SRS Watch. Materials published on this website are for non-profit public interest purposes only. SRS Watch is a registered corporation in South Carolina and in December 2014 and has obtained non-profit 501(c)(3) public -interest organization status from the IRS. SRS Watch is responsible for all material published on this website. We strive to be accurate in all material produced. For inquiries, comments or corrections, please contact us at srswatch@gmail.com or 803-834-3084. Donations are most welcome and are tax deductible. Mailing address: Savannah River Site Watch, 1112 Florence Street, Columbia, SC 29201. This site or product includes IP2Location LITE data available from https://lite.ip2location.com.

©SRS Watch 2019  All Rights Reserved in All Media.