• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
  • Skip to footer

Savannah River Site

Monitors a host of energy and nuclear issues from a public interest perspective

  • Home
  • About Us
  • News
  • SRS Watch News
  • Library
    • Department of Energy
    • General Documents
    • Freedom of Information Act Documents
  • Photos
  • Show Search
Hide Search

MOX-Style Disaster Unleashed? NNSA Gives Failing Grade to Construction of SRS Plutonium Bomb Plant by Savannah River Nuclear Solutions

SRSW · March 26, 2026 ·

DOE’s National Nuclear Security Administration (NNSA) has released the “Performance Evaluation Report” (PER) for the work in Fiscal Year 2025 of the SRS plutonium Bomb Plant contractor, Savannah River Nuclear Solutions (SRNS), and the performance of SRNS was POOR.  This PER look like those that were issued as the plutonium fuel (MOX) project was falling apart a decade ago.

This sentence in the introduction says it all:  “SRNS underperformed in project execution of the Savannah River Plutonium Processing Facility
(SRPPF) project in FY 2025.”  Thus, the project costs are certain to continue to go up and the schedule further delayed.

SRNS garnered but 40% of the potential award fee (bonus), an abysmal performance given that the award fees given by DOE to contractors are usually near 100%.

Something that raises red flags in the PER is that there is no indication given as to when the next cost estimate and near-completion of the pit plant (Critical Decsion-2/3) will be issued. NNSA had submitted documents in our successful complaint in federal court – that resulted in a Programmatic EIS being prepared (draft PEIS ste to be released i n May 2026) – that CD-2/3 would be issued in late 2025.

Will funding in Fiscal Year 2027 be at risk, as stated in  he PER?  We can only hope so and that the project is terminated before more billions of $ are needlessly wasted on the $35 billion pit plant (the most expensive building in U.S. history!), all in the name of making new nuclear warheads to fuel a new nuclear arms race.

National Nuclear Security Administration
Savannah River Nuclear Solutions, LLC
Performance Evaluation Report
Contract No. DE-AC09-08SR22470
Savannah River Field Office
Evaluation Period:
October 1, 2024, through September 30,
2025
December 9, 2025
https://www.energy.gov/sites/default/files/2026-02/SRS%20FY%202025%20Performance%20Evaluation%20Report.pdf
excerpts:
page 2
SRNS underperformed in project execution of the Savannah River Plutonium Processing Facility
(SRPPF) project in FY 2025.
Going into FY 2025, the plan was for SRNS to drive the project through
the transfer of project leadership to an experienced construction manager (CM), issue and start CD-3X
package construction scope, demonstrate funding execution via those CD-3X packages, and issue a CD
2/3 package supporting full cost/schedule approval. The project has seen a few benefits from the CM
transition, but they are minimal. The planned CD-3X packages pushed well past scheduled dates with
minimal work executed in FY 2025. The CD 2/3 submittal for the HFTOC package was successful, but
the overall project cost/schedule submittal pushed into FY 2026, negatively impacting NNSA efforts to
forecast FY 2026 funding needs while adding risk to FY 2027 funding.
The SRPPF design failed to
meet 60 percent complete requirements when issued in October 2025, and the Design Gate 3 date was
pushed out by 8 months. Complete designs are required to feed construction scope in the field, and
these delays are limiting future work fronts into FY 2026.
pages 13-14
SRNS supported the SRPPF project through effective interactions with external stakeholders   [Tom: say what?!]
during project reviews, site visits, and tours
. SRNS provided support through all phases of
preparation for these events including coordination of on-site logistics, management of requested
information, prompt and thorough responses to questions and lines of inquiry, preparation and13
participation in meetings, and tracking and completion of action items resulting from these
interactions. Specific examples include support, management and execution of the Technical
Independent Project Review (TIPR); multiple site visits and tours by key leaders and external
stakeholders.
page 14
Issues
As of August 2025, SRNS has spent $1.07 billion but has only claimed an earned value of
$971M for that scope of work
. Approximately half of the positive cost performance comes from
level-of-effort accounts like CM indirect and SRNS oversight. However, SRNS
is experiencing poor performance with discrete tasks such as Glovebox Fabrication/Design.
Despite showing a positive cost variance for the fiscal year, CD-3C (Concrete Penetrations)
execution is projected by NNSA/SRNS to require an additional $250-300M to complete the
Energy Systems Acquisition Advisory Board (ESAAB)-approved scope. It was not until July
2025 that SRNS verbally notified NNSA that CD-3C will exceed the ESAAB-approved amount.

This overrun had been anticipated and communicated as a concern by NNSA for months, based
on the tracking of Task Order Awards (TOAs) awarded under the Indefinite Delivery/Indefinite
Quantity (IDIQ) contract and related scope. To prevent such issues, SRNS should enhance its
oversight of CM-awarded contracts and provide timely information to NNSA to ensure proper
decision-making to set the project on a course for success.
SRNS procurement was consistently slow in the first half of the year to meet data requests from
NNSA.
NNSA has had to ask multiple times for subcontracts to support local reviews. These
delays however have been reduced over the last few months.
page 15
Issues:
SRNS finish adherence to the forecast and baseline schedules for self-performed scope in FY
2025 was well below the desired level of 95 percent adherence based on the DOE Project
Assessment and Reporting System excerpt. For FY 2025, only 47 percent of activities were
completed as forecasted, and only 17 percent were completed as baselined.
SRNS project reporting has not provided adequate context of overall project status. Reporting
lists accomplishments and some discrete issues/challenges, but the reports give no sense of the
magnitudes of schedule delays and cost overruns that have been experienced during the
performance period. The lack of recognition and acknowledgement of issues results in a
corresponding lack of communication of recovery plans.
In finalizing the design for the Y810 project, SRNS failed to effectively manage the interfaces
among the organizations. When NNSA directed descoping of Y810 from SRNS (NNSA-SRPPF-
24-0200), the direction stated “Your support of this acquisition strategy revision as the SRPPF
project Design Authority (DA) and SRNS Site M&O contractor remains critical to the success of
the SRPPF project. Your continued support is required.” Further, the FY’25 Award Fee Plan,
under Subjective Fee Area 2, states “The Contractor shall support the NNSA by working with the
United States Army Corp of Engineers (USACE) to deliver all infrastructure and logistical
services required for successful USACE execution…”. However, as documented in NNSA-
SRPPF-25-0173, SRNS was unresponsive in supporting the resolution of identified interface
issues between the USACE and Fluor designs from June through August, hampering successful
USACE execution of the project.
page 17
Issues:
The Y799 Main Process Building (MPB) Integrated Master Schedule (IMS) submitted on May
29, 2025, was determined by the Independent Cost Estimate (ICE) team to be of insufficient
quality to continue the ICE process. The inability of SRNS to develop a quality baseline
submittal has negatively impacted NNSA’s ability to appropriately plan and fund the project.
This issue has resulted in reductions in project funding that will further delay project completion.
The 3X package early submittals have continued to slip throughout FY 2025. This reduces the
benefit of having CD-3X package scopes to accelerate field work on critical path scope
, or aid in
leveling the amount of onsite personnel at peak execution. The dates below demonstrate the slip
in CD-3X package submittals to initiate the process of approval throughout FY 2025. The
commitment dates are based on the agreement reached between SRNS and NNSA in letter
SRNS-F2000-2024-00049. The revised commitment dates are from the latest commitment from
SRNS to NNSA in letter SRNS-F2000-2025-00205.
Incentive fee available $32,058,582 
 
Incentive fee awarded $12,829,529
Photo of SRS Plutonium Bomb plant when it was the MOX plant, by High Flyer; Pit plant sign – photo by DOE

Filed Under: Latest News

Primary Sidebar

Subscribe to Updates via Email

Enter your email address to subscribe to updates and receive notifications of new posts by email.

Recent Posts

  • News Media on the Plutonium Pit Production PEIS – Finally the Issue Breaks Through & the Public Can Learn about the Threats of Plutonium “Pit” Production to Fuel New Nuclear Warheads
  • Thoughts on Touring the $30-Billion SRS Plutonium Bomb Plant…not as Sweet as Willy Wonka’s Chocolate Factory, April 21, 2026
  • “Impacts of plutonium pit production at Savannah River Site unveiled” – article on Plutonium Pit Plant PEIS, April 20, 2026
  • Comment to DOE on Impacts of SRS Plutonium Bomb Plant; Update on Bomb Plant Tour at SC State Capitol on April 22
  • MOX-Style Disaster Unleashed? NNSA Gives Failing Grade to Construction of SRS Plutonium Bomb Plant by Savannah River Nuclear Solutions

Categories

  • Events
  • Latest News
  • SRS Watch News

Archives

  • April 2026
  • March 2026
  • February 2026
  • November 2025
  • October 2025
  • September 2025
  • August 2025
  • July 2025
  • May 2025
  • April 2025
  • March 2025
  • February 2025
  • January 2025
  • December 2024
  • November 2024
  • October 2024
  • September 2024
  • May 2024
  • April 2024
  • March 2024
  • February 2024
  • January 2024
  • December 2023
  • November 2023
  • October 2023
  • September 2023
  • August 2023
  • July 2023
  • June 2023
  • May 2023
  • April 2023
  • March 2023
  • February 2023
  • January 2023
  • November 2022
  • October 2022
  • September 2022
  • July 2022
  • June 2022
  • May 2022
  • April 2022
  • March 2022
  • February 2022
  • January 2022
  • December 2021
  • November 2021
  • October 2021
  • September 2021
  • August 2021
  • July 2021
  • June 2021
  • May 2021
  • April 2021
  • March 2021
  • February 2021
  • January 2021
  • December 2020
  • November 2020
  • October 2020
  • September 2020
  • August 2020
  • July 2020
  • June 2020
  • May 2020
  • April 2020
  • March 2020
  • February 2020
  • January 2020
  • December 2019
  • November 2019
  • October 2019
  • September 2019
  • August 2019
  • July 2019
  • June 2019
  • May 2019
  • April 2019
  • March 2019
  • February 2019
  • January 2019
  • December 2018
  • November 2018
  • October 2018
  • September 2018
  • August 2018
  • July 2018
  • June 2018
  • May 2018
  • April 2018
  • March 2018
  • February 2018
  • January 2018
  • December 2017
  • November 2017
  • October 2017
  • September 2017
  • August 2017
  • July 2017
  • June 2017
  • May 2017
  • March 2017
  • February 2017
  • January 2017
  • December 2016
  • November 2016
  • October 2016
  • September 2016
  • August 2016
  • July 2016
  • June 2016
  • May 2016
  • April 2016
  • March 2016
  • February 2016
  • January 2016
  • December 2015
  • November 2015
  • October 2015
  • September 2015
  • August 2015
  • July 2015
  • June 2015
  • May 2015
  • April 2015
  • March 2015
  • February 2015
  • January 2015
  • December 2014
  • November 2014
  • October 2014
  • September 2014
  • August 2014
  • July 2014
  • June 2014
  • May 2014
  • April 2014
  • March 2014

SAVANNAH RIVER SITE WATCH
1112 Florence Street, COLUMBIA, SC 29201  | 803-834-3084  – srswatch@gmail.com

Footer

The information produced on this website is the sole property of SRS Watch unless otherwise noted and may be reproduced or quoted if credit is given to SRS Watch. Materials published on this website are for non-profit public interest purposes only. SRS Watch is a registered corporation in South Carolina and in December 2014 and has obtained non-profit 501(c)(3) public -interest organization status from the IRS. SRS Watch is responsible for all material published on this website. We strive to be accurate in all material produced. For inquiries, comments or corrections, please contact us at srswatch@gmail.com or 803-834-3084. Donations are most welcome and are tax deductible. Mailing address: Savannah River Site Watch, 1112 Florence Street, Columbia, SC 29201. This site or product includes IP2Location LITE data available from https://lite.ip2location.com.

©SRS Watch 2019  All Rights Reserved in All Media.