SRS Watch news of May 6, 2014
DOE Analysis on Plutonium Disposition Incorrect in Stating Not Enough High-Level Waste Remains at Savannah River Site for Immobilization of 34 Metric Tons of Plutonium
“….the MOX project will be placed in cold stand-by, meaning we will cease all construction activities in order to minimize costs.”
Plutonium Disposition Working Group: Analysis of Surplus Weapon‐Grade Plutonium Disposition Options, April 29, 2014 – MOX life-cycle cost is an unsustainable $30 billion or more, MOX plant construction $10 billion or more
FOIA Document Indicates Discussions Began in 2011 for Import of Graphite Spent Fuel from Shuttered Gas-Cooled Experimental Power Reactor – to DOE’s Savannah River Site – April 29, 2014