Report outlines MOX Challenges; MOX Updates

SRSW · May 9, 2015 ·

Redacted DOE Plutonium Disposition Report Obtained, Gives Details of $47.5 Billion to $110.4 Billion Yet to be Spent on Plutonium Fuel (MOX) Boondoggle, Finished in 2059 to 2115

Aerospace Report Affirms that MOX Project at SRS Not Sustainable at Current Funding Level

“Plutonium Disposition Study Options Independent Assessment”

redacted report linked here:

https://www.srswatch.org/uploads/2/7/5/8/27584045/aerospace_final_redacted_plutonium_disposition_tor_april13_final_release_050815.pdf

news release linked here

photos: MOX plant, April 21, 2015, by High Flyer of the SRS Watch Air Force, can be used with credit; in one photo Georgia Power’s Plant Vogtle in Georgia, site of two old reactors and two AP1000s under construction, can be seen

—–

NNSA dribbles out environmental document on terminating MOX as “preferred alternative,” via tiny notice in Federal Register by Environmental Protection Agency, May 8, 2015

“EIS No. 20150125, Final Supplement, NNSA, DOE, Surplus Plutonium Disposition, Review Period Ends: Once a Preferred Alternative is identified, DOE will announce its preference in a Federal Register notice. DOE would publish a record of decision no sooner than 30 days after its announcement of a Preferred Alternative. Contact: Sachiko McAlhany 877-344-0513″

linked here

—-

SRS Watch new release, May 4, 2015 – release linked here

<strong “mso-bidi-font-weight:=”” normal”=””>After Chronic Delays, DOE’s Terminates Plutonium Disposition EIS Process, Discarding the Problem-Plagued Plutonium Fuel (MOX) Option as the “Preferred Option” and Affirming that the Tennessee Valley Authority (TVA) is Not Now Actively Pursuing MOX Use
<strong “mso-bidi-font-weight:=”” normal”=””>
<strong “mso-bidi-font-weight:=”” normal”=””>CB&I AREVA MOX Services Dealt another Blow in its Push for $51+ Billion MOX Project<strong “mso-bidi-font-weight:=”” normal”=””>

<strong “mso-bidi-font-weight:=”” normal”=””><span “font-size:12.0pt;=”” line-height:107%”=””>Surplus Plutonium Disposition Supplemental EIS documents linked here – quietly placed on this DOE website in the last few days

Columbia, South Carolina — After a lengthy and embarrassing delay, the U.S. Department of Energy DOE) has concluded the preparation of an environmental document on the disposition of surplus weapons plutonium by abandoning its earlier preference to produce plutonium fuel (MOX) from the material. DOE states in a document released over the weekend that it no longer has a preference for how to dispose of a quantity of surplus plutonium, affirming that the MOX program at the DOE’s Savannah River Site (SRS) in South Carolina remains at high risk of being shut down.

DOE’s National Nuclear Security Administration (NNSA) had been expected to issue the final environmental document in early 2013 but due to growing problems with the MOX program, DOE froze release of it and indicated for almost two years that it was “under departmental review.” DOE mailed out DVDs with the documents, which arrived to at least one location in South Carolina on Saturday, May 2.  DOE also quietly posted the final documents on its website in the last few days. The date of a Federal Register notice on the formal release of the document is expected later this week.

<span “font-size:11.0pt;line-height:107%;font-family:”calibri”,sans-serif;=”” mso-ascii-theme-font:minor-latin;mso-fareast-font-family:calibri;mso-fareast-theme-font:=”” minor-latin;mso-hansi-theme-font:minor-latin;mso-bidi-font-family:”times=”” roman”;=”” mso-bidi-theme-font:minor-bidi;mso-ansi-language:en-us;mso-fareast-language:=”” en-us;mso-bidi-language:ar-sa”=””>In complete reversal of DOE’s earlier pro-MOX policy, the final Surplus Plutonium Disposition Supplemental Environmental Impact Statement (SPD SEIS) concludes that DOE no longer prefers the MOX option but rather states that it has no “preferred alternative” for plutonium disposal “at this time.”

read full release here, with loads of links to documents and MOX plant photos

—–

May 2, 2015  Congressional boosters of MOX again requested by SRS Watch to release their validated life-cycle costs for the MOX project.  Where are their cost estimate and why are they withholding them from the discussion about the fate of the project?

The MOX-booster-members of Congress stand virtually alone in Congress in their blind allegiance to continue shoveling our tax money to CB&I AREVA MOX Services. While they choose to attack DOE’s cost estimates for the $50+ billion MOX boondoggle looks like they don’t even have their own validated MOX cost estimates on which to base their attacks.  We asked them before and they came up empty handed. We doubt they have anything now but the ball is in the court of Senator Lindsey Graham, Senator Tim Scott & Representative Joe Wilson to respond. As is said, time to put up or shut up about this failed and dying project. BTW, $345 million in FY 2016 puts the project on a shut-down track as it needs another $200 million per year for construction (and $800 million/year during MOX plant operation) and even Congress is smart enough not to waste that much more of our money on this massive debacle.

letters to Graham, Scott & Wilson linked here

—-

SRS Watch has released a new update on the MOX Boondoggle – April 29, 2015 – the storm clouds over the failed project continue to gather

In this update – linked here:

<span “font-size:12.0pt;line-height:=”” 107%”=””>— SRS Watch Again Requests Validated MOX Cost Analysis from AREVA and CB&I AREVA MOX Services, No Response Expected

— DOE Set to End Long-Delayed Plutonium Supplemental EIS Process with No Decision; Document “under departmental review” to be terminated with no “preferred alternative,” harming MOX

— FOIA Request Filed by SRS Watch for DOE Plutonium Cost Study Sent to Congress on April 22; Aerospace Corporation cost document must be released in full

— Nuclear Regulatory Commission (NRC) Alerted to Possibly Faulty Embed Plates for MOX plant – will the NRC investigate or ignore?

— Rumors on MOX Plant Construction Problems Continue – With Only One (1) On-Site NRC Inspector, Who is Investigating and Who is Properly Monitoring Overall MOX plant Construction?  With the NRC inspecting only a small sample of only some components, CB&I AREVA MOX Services is self-regulating its own work!

Update linked here

—–

April 28, 2015 – While DOE has said that a redacted copy of the plutonium disposition cost report (by Aerospace Corporation) delivered to Congress on April 22 will be eventually released, SRS Watch has gone ahead and filed a Freedom of Information Act (FOIA) request for it. By law, DOE has to respond within 20 days.   See the FOIA request linked here.

Though DOE is slowly releasing more cost information, CB&I AREVA MOX Services still adamantly refuses to release any validated MOX life-cycle cost analysis it has for the MOX project it has so badly managed. 

Habitual failure to ever release its own cost analysis validated by external, credible parties means that anything that AREVA or CB&I has to say about any aspect of costs for MOX construction, start-up or operation has no basis and should be ignored.  We now feel that they have no life-cycle cost estimate for any aspect of the project.  If they do, AREVA must release it.  If not, their already low credibility will sink further.

See request for validated MOX life-cycle cost to AREVA, Inc. North America CEO and president here and for request to the VP of the “Backend Division North America” click here. 

Letter to David Del Vecchio, president, CB&I AREVA MOX Services

In a rather desperate response to the summary of costs by Aerospace, VP David Jones has written about why the experimental weapon-grade MOX fuel project is so great but his totally ignoring costs issues sticks out a like a big, embarrassing sore thumb.  Quch!   Mr. Jones, we suggest that you give it another shot and quote in your next article from AREVA’s validated, public cost estimate for the MOX plant construction, start-up and operation.

By the way, all the AREVA lobbying on the Hill with unions only confirms that the MOX project is a parochial jobs program. AREVA, be careful with that approach in your desperate efforts to save the MOX boondoggle.

NRC letter to SRS Watch, April 1, 2015 – admitting that only certain parts of the MOX plant are being inspected.  So, is anyone adequately inspecting the MOX plant construction?  With only one (1!) on-site, resiodent inspector, how can the NRC be doing a though job?  Sounds like NRC inspection is cursory at best and excludes many parts of MOX construction.

Filed Under: SRS Watch News

Primary Sidebar

Subscribe to Updates via Email

Enter your email address to subscribe to updates and receive notifications of new posts by email.

Recent Posts

  • Workshop on Plutonium Pit Production PEIS & New Nuclear Weapons: May 22, 2025
  • News Flash! Lawsuit Compels Nationwide Public Review of Plutonium Bomb Core Production by DOE’s NNSA, May 9, 2025 Federal Register
  • Talk on SRS, the Nuclear Arms Race & Upcoming Meetings on Plutonium “Pit” Production – May 10, Columbia, SC & livestream archived
  • SRS & Growing Nuclear Weapons Role: Talks April 28 (Aiken, SC) – with linked presentation – and May 10 (Columbia, SC)
  • Excellent article on NNSA’s scheme to make new plutonium pits: “DOGE’s staff firing fiasco at the nuclear weapon agency means everything but efficiency,” April 16, 2025, Bulletin of Atomic Scientists

Categories

  • Events
  • Latest News
  • SRS Watch News

Archives

  • May 2025
  • April 2025
  • March 2025
  • February 2025
  • January 2025
  • December 2024
  • November 2024
  • October 2024
  • September 2024
  • May 2024
  • April 2024
  • March 2024
  • February 2024
  • January 2024
  • December 2023
  • November 2023
  • October 2023
  • September 2023
  • August 2023
  • July 2023
  • June 2023
  • May 2023
  • April 2023
  • March 2023
  • February 2023
  • January 2023
  • November 2022
  • October 2022
  • September 2022
  • July 2022
  • June 2022
  • May 2022
  • April 2022
  • March 2022
  • February 2022
  • January 2022
  • December 2021
  • November 2021
  • October 2021
  • September 2021
  • August 2021
  • July 2021
  • June 2021
  • May 2021
  • April 2021
  • March 2021
  • February 2021
  • January 2021
  • December 2020
  • November 2020
  • October 2020
  • September 2020
  • August 2020
  • July 2020
  • June 2020
  • May 2020
  • April 2020
  • March 2020
  • February 2020
  • January 2020
  • December 2019
  • November 2019
  • October 2019
  • September 2019
  • August 2019
  • July 2019
  • June 2019
  • May 2019
  • April 2019
  • March 2019
  • February 2019
  • January 2019
  • December 2018
  • November 2018
  • October 2018
  • September 2018
  • August 2018
  • July 2018
  • June 2018
  • May 2018
  • April 2018
  • March 2018
  • February 2018
  • January 2018
  • December 2017
  • November 2017
  • October 2017
  • September 2017
  • August 2017
  • July 2017
  • June 2017
  • May 2017
  • March 2017
  • February 2017
  • January 2017
  • December 2016
  • November 2016
  • October 2016
  • September 2016
  • August 2016
  • July 2016
  • June 2016
  • May 2016
  • April 2016
  • March 2016
  • February 2016
  • January 2016
  • December 2015
  • November 2015
  • October 2015
  • September 2015
  • August 2015
  • July 2015
  • June 2015
  • May 2015
  • April 2015
  • March 2015
  • February 2015
  • January 2015
  • December 2014
  • November 2014
  • October 2014
  • September 2014
  • August 2014
  • July 2014
  • June 2014
  • May 2014
  • April 2014
  • March 2014

SAVANNAH RIVER SITE WATCH
1112 Florence Street, COLUMBIA, SC 29201  | 803-834-3084  – srswatch@gmail.com

Footer

The information produced on this website is the sole property of SRS Watch unless otherwise noted and may be reproduced or quoted if credit is given to SRS Watch. Materials published on this website are for non-profit public interest purposes only. SRS Watch is a registered corporation in South Carolina and in December 2014 and has obtained non-profit 501(c)(3) public -interest organization status from the IRS. SRS Watch is responsible for all material published on this website. We strive to be accurate in all material produced. For inquiries, comments or corrections, please contact us at srswatch@gmail.com or 803-834-3084. Donations are most welcome and are tax deductible. Mailing address: Savannah River Site Watch, 1112 Florence Street, Columbia, SC 29201. This site or product includes IP2Location LITE data available from https://lite.ip2location.com.

©SRS Watch 2019  All Rights Reserved in All Media.